Site Planning Concepts
The Current Campus Idea
A compact residential village and a substantial robotics and technical center are the current starting points for planning the 18.96-acre Sands Drive site.
The initial housing concept uses two four-story buildings with approximately 320 beds, while preserving a significant portion of the property for robotics laboratories, shops, classrooms, industry collaboration, parking, circulation, and future expansion.
The plan is intentionally not fixed. Housing absorption, suite design, parking demand, building footprints, engineering, and the ultimate robotics program all require additional work. The objective at this stage is to establish a coherent campus framework that can accommodate those decisions as the project advances.
Residential
320-Bed Residential Starting Point
The present starting concept, not a final commitment:
| Item | Value |
|---|---|
| Buildings | 2, four stories each |
| Suites per floor | 10 |
| Suites per building | 40 |
| Total suites | 80 |
| Students per suite | 4 |
| Beds per building | 160 |
| Total beds | 320 |
A future third building remains an expansion option only. The Phase I case is the two-building, 320-bed program above; if a third building is added later using the same configuration, total suites would rise to approximately 120 and total beds to approximately 480.
Demand context
Fall 2025 enrollment figures for Albany State University, per the university's own Fall 2025 Quick Facts Report:
| Metric | Approx. |
|---|---|
| Total students | 6,820 |
| Undergraduates | 6,167 |
| First-time freshmen | 1,457 |
| Freshmen (all) | 2,376 |
| Sophomores | 1,497 |
| Freshmen + sophomores combined | 3,873 |
The first-time freshman class was approximately 72% women, 28% men. The 320-bed concept is therefore approximately 22% of one first-time freshman class, or 8% of the combined freshman/sophomore population.
These ratios are useful context. They do not prove absorption, and the project does not claim all 320 beds will automatically be filled. The design should stay operationally flexible - suites, floors, wings, or buildings assignable by actual enrollment and demand over time, not hard-coded to a permanent gender-specific split.
Suite Concept
Four-Person Suite Concept
These are planning-stage student suites, not conventional double-occupancy dorm rooms - four residents per suite, each with a private bedroom and a private bathroom. A first-pass suite size is approximately 1,200 to 1,400 square feet as a planning range; final unit design is still to be determined.
The working layout is a four-bedroom, four-bathroom suite: four private bedrooms, each with its own bed, desk, dresser, closet, and private bathroom; a shared living area; and an open kitchen with a dining area. This mirrors a proven configuration used in university-oriented housing - for example, the four-bed, four-bath suite at University Suites near NC State (roughly 1,398 square feet). The private-bathroom concept is intentional: the product is not being conceived as the cheapest possible institutional bed, and the working thesis is that a better-quality residential product can improve absorption, resident satisfaction, durability, and pricing power. That thesis is not yet proven economics. Final dimensions, fixtures, and kitchen configuration remain to be set in design.
Building scale, conceptual
At approximately 10 suites per floor and roughly 1,200 to 1,400 SF per suite, net suite area per floor is on the order of 12,000 to 14,000 SF. Gross building area per floor will be higher after common circulation, stairs, elevators, walls, mechanical areas, laundry, lounges, and service space.
| Item | Conceptual range |
|---|---|
| Gross SF per floor | 15,000-17,500 |
| Gross SF per 4-story building | 60,000-70,000 |
| Gross SF, both buildings | 120,000-140,000 |
These are planning figures only, labeled conceptual/approximate. No detailed floor plan or engineered building design exists yet.
Robotics + Technical
Robotics + Technical Innovation Center
The robotics building is a major part of the concept, not secondary space left over after housing. The working vision is a substantial university-style building - brick or masonry campus character, significant windows, institutional proportions, a substantial entrance, durable materials, a landscaped setting. Not a generic industrial warehouse.
Possible functional program (TBD)
The functional program may eventually include robotics laboratories, prototype development areas, machine and fabrication shops, high-bay work areas, classrooms, instructional laboratories, faculty or program offices, meeting rooms, collaboration space, demonstration areas, loading and service access, secure areas for equipment and prototypes, and space for outside robotics or technology companies to temporarily work on prototypes, testing, research, or joint projects.
Outside industry participation is a development concept, not a committed partnership - no company is identified or implied to have agreed to participate.
Parking + Movement
Parking and Movement
Parking is one of the major site-planning constraints. The combined program may generate a substantial number of cars from student residents, faculty, staff, robotics students, visitors, industry partners, prototype or service vehicles, and deliveries. No final parking count exists - this page does not show one.
Planning should consider shared parking between uses where schedules allow, compact surface parking, pedestrian connections, safe student walking routes, bicycle access, service access, loading areas separated from residential activity, future structured parking only if economics eventually justify it, and preserving land from being consumed unnecessarily by surface parking.
Phasing
Room to Grow
Phase I - current working case
Two 4-story student housing buildings (~320 beds), the robotics/technical innovation center, required parking and circulation, site infrastructure, landscaping, stormwater, and a preserved expansion area where practical.
Future expansion - possible, not committed
Potential future additions may include a third residential building, robotics building expansion, additional laboratories or industry space, additional parking solutions, and other education or workforce-development uses. None of this is shown as committed construction.
Open Items
What We Still Need to Determine
- Final suite design and final suite size
- Housing pricing
- A formal absorption study
- Exact robotics building program and square footage
- Building footprints
- Parking requirement
- Civil circulation, stormwater, and utility layout
- Architectural design
- Final phasing
- Relationship with Albany State University
- Financing and ownership structure
These gaps are not filled with invented assumptions on this page or elsewhere on the site. See also What Comes Next on the main page for the parallel development-process list (site control, absorption, entitlement, engineering, stakeholders, capital).